Monday, January 4, 2016

The Hahnville High School Weight Training and Exercise Building is Substantially Complete




The Hahnville High School Weight Training and Exercise Building has been substantially completed by Crescent Commercial Construction on October 19th, 2015, for St Charles Parish Public Schools, in Boutte, Louisiana.

This brick-clad CMU building consists of 6900 square feet of built area, all on one floor, and contains a weight room and a general exercise room, with a retractable batting cage system, as well as restrooms and other support spaces.

Construction took nine and a half months, since January 5th, 2015, and has been substantially completed on schedule.  Including the eight months of design, the entire length of the project has been 18 months.

The final building cost of the project was $1,206,100, or $175/SF, after separating out the other building.  On the overall project, including both buildings, there was over $70,000 worth of savings during construction via change orders, or 2.4% of the bid cost of $2,869,000.

We thank St Charles Parish Public Schools and Crescent Commercial Construction for working with us on the project, and wish them the best in the future.

No comments:

Post a Comment