St Charles Parish Public Schools received bids for Lakewood elementary school interior renovation on January 12, 2016. HMS had previously finished the drawings and specifications for Building for St Charles Parish Public Schools, on schedule after 5 months of design work.
The Lakewood Elementary School Building A Renovations consist of 26,756 SF of renovated area, all on the first floor, and this renovation modifies a large shared classroom area, separated by temporary partitions, splitting the area into 19 new classrooms and a teacher work area suite, using high-impact gypsum board on metal stud framing, for durability in the demanding educational environment.
When including all alternates, the five bids ranged from $1.4M to $1.9M. within 35% of each other, reflecting the uncertainty of renovation projects. The winning bid was for $1,401,000, or $51 per square foot, which is under budget by $399,000 or more than 20%. This difference allowed all alternates to be accepted within the budget.
The winning Contractor, Dynamic Constructors , is expected to begin work in late May, for a contract length of 60 days, expecting to finish by the start of school. We look forward to working with St Charles Parish Public Schools and Dynamic Constructors for the months ahead.
More Information about the Lakewood Elementary School Building A Renovations
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment