The Lakewood Elementary School Building A Renovations were completed by Dynamic Constructors in late July, for St Charles Parish Public Schools, in Luling, Louisiana.
This existing steel-framed, concrete block building consists of 26,700 SF of renovated area, all on the first floor. The renovation modified a large shared classroom area, separated by temporary partitions, and split the area into 19 new classrooms and a teacher work area suite. Meeting the owner's desire for durable materials in this demanding education environment the design team used high-impact gypsum board on metal stud framing for the new walls. This project also included new ceilings, and floor finishes, as well as adapting the existing mechanical and electrical equipment to the new layout with new light fixtures and ducts. Overall, the project ended up costing $51/SF.
Working with the owner's desire to not lose any space during the school year the project was designed to have construction occur over the summer months when students would not be in class. Construction started after completion of the spring semester in May 2016 and was completed just ahead of schedule, allowing the owners ample time to re-occupy the space and prepare for the fall semester.
The final building cost of the project is more than 20% under the original budget, both due to a good bid at the outset, and by diligent construction administration, keeping the change orders well within 1% of the overall bid cost.
We thank St Charles Parish Public Schools and Dynamic Constructors for working with us on this successful project, and wish them the best in the future.
No comments:
Post a Comment