The Allemands Elementary School Classroom Addition is Substantially Complete




The Allemands Elementary School Classroom Addition has been substantially completed by F. J. Arcement Construction Co. Inc. on May 2nd, 2016, for St Charles Parish Public Schools, in Des Allemands, Louisiana.

This brick-clad, steel-framed, metal stud building consists of 6230 SF of additional built area added onto a 27,000 SF existing building, both all on one floor.   The addition contains 4 additional classrooms, including an art classroom, as well as a work room, restrooms, and support spaces.  The building cost about $175 per square foot overall.

Construction took 11 Months, since June 8, 2015, and has been substantially completed ahead of schedule.  Including the 9 Months of design, the entire length of the project has been 20 months.

The final building cost of the project was within 10% of the original budget, which was helped by finding about 1% of savings via change orders by careful construction administration.

We thank St Charles Parish Public Schools and F. J. Arcement for working with us on the project, and wish them the best in the future.